Friday, March 8, 2013

We made good progress Friday, with all of the lower level walls framed and sheathed, and the beams in place to start the second floor framing.  We had a tropical downpour nearly all night Wednesday, so the humidity has been overwhelming (for me at least) but the daily sauna treatment is all part of the Haiti diet plan!  Today the skies have cleared and we're supposed to have several days of lower humidity and no chance of rain.  Tomorrow we should start the second floor and I hope to have that finished by Monday evening.  Our next container load of materials is supposed to clear customs on Monday, so we'll have more materials on site.  Container #3 just arrived in port from Freeport, Bahamas where it's been languishing for the past couple of weeks waiting for a boat to Port au Prince.